Featured Project #1
Featured
Project #1: Oakland Raiders
Distribution Center, San Leandro,
CA

|
Summary: The Oakland
Raiders planned to open a new
26,000 square foot distribution
center to support their Raider
Image stores, as well as
e-commerce. The TMH Systems Group
was asked in April to complete the
project by September with a budget
of $300,000.
Concept Development began
in April. The agreed upon system
was to be made up of rack,
conveyor, decking and trucks.
Details: After finalizing
the design, the TMH Systems Group
provided all of the required
upgrades to the facility that were
needed to pass the permit process,
including fire code compliance and
structural engineering to meet
California’s strict codes for
earthquake protection.
Implementation: The
distribution center was equipped
with several different types of
material handling equipment
including flow rack and pallet
racks from Interlake Material
Handling Solutions, an
Ermanco conveyer system, wire
mesh decking from ITC
Manufacturing and two Toyota
Lift Trucks. Everything was
painted silver and black to match
the Raider’s signature colors.
Conclusion: Implementation
of this fast track project began
in July and was completed in early
September on budget.